Modernization of Electrical Devices and Automation of 350 Rolling mill

Employer : Esfahan Steel Co.
Provoided Service : Construction, installation and connection of 30 sets marshaling panels in Agglomeration, signal checking
Duration : 3 months
Employer Address : the End of Superhighway ESCO. , Esfafan. Tel: 0334-2573333

70%
Completed

Modernization of Electrical Devices and Automation of 350 Rolling mill

Employer : Esfahan Steel Company
Provoided Service : Procurement of control system, instrumentation & drives by using S7-400H series of siemens PLC.Software preparing based on PCS7 Ver 8.1, Installation, I/O check and commissioning of rolling mill.
Duration : 14 Month
Employer Address : End of Superhighway ESCO. , Esfafan. Tel: 031-52573333

Installation and commissioning of electrical systems for Esfahan City Center Project

Employer : Iran Prestige Land Co.
Provoided Service : Installation and commissioning of MV and LV electrical equipment consist of 13 sets trans, 20KV: 400V, 5 km Bus duct, 80 km cable tray, 350 km cable, lighting system, BMS equipment and …
Duration : 30 months
Employer Address : North Railway Station Esfahan, Opposite of Southern Entrance of Sepahan Shahr, East of Vahid Dastjerdi Highway, Esfahan. Tel: 0311-6541900

186
Completed
189
Completed

Programming services and commissioning of automation system in Bafgh Agglomeration Project

Employer : Central Iron Ore Company
Provoided Service : Software preparing, signal checking, testing and commissioning based on S7-400H Siemens hardware and PCS7 V8.0 software
Duration : 8 months
Employer Address : Bafgh Town, Yazd

Positioning machines system in Esfahan Steel Coking Plant

Employer : Esfahan Steel co.
Provoided Service : Design, prroviding, construction, installation and commissioning of communication and positioning systems for 8 species machines of No. 3 battery consist of PLC hardware and software based on S7-400H Siemens hardware and Siemens PCS7 software and radio communication equipment, Siemens MOBY D to EPC
Duration : 10 months
Employer Address : End of Superhighway ESCO. , Esfafan. Tel: 0334-2573333

187
Completed
188
Completed

DCS system upgrading from PCS7 VER5.2 to PCS7 VER7.1 in Steel Making of ESCO.

Employer : Esfahan Steel Co.
Provoided Service : Providing of Siemens industrial computers and version upgrading of PCS7 software from version 5.2 to version 7.1 in the steel making boilers, removing the existing bugs, testing and commissioning of boilers
Duration : 6 months
Employer Address : End of Superhighway ESCO. , Esfafan. Tel: 0334-2573333

Design, providing, Installation and commissioning of control system and instrumentation in Jask Water Treatment

Employer : Zharf Kar-e Jam Co.
Provoided Service : Design and preparing of control system and monitoring based on S7-300 Siemens hardware
Duration : 12 months
Employer Address : No.123, Mehrdad building, Eastern Allameh Amini St. , Allameh Amini Intersection, 22 Bahman St. , Esfahan. Tel: 0311-2616516

Completed
197
Completed

Providing, installation and commissioning of automatic control system for valves of Zayande Roud Regulatory Dam

Employer : Esfahan Regional Water Co.
Provoided Service : Remote control of regulatory dam valves by GPRS system and S7-1200 Siemens control system
Duration : 4 month
Employer Address : Beginning of Aynehkhaneh Blvd. , Esfahan. Tel: 0311-6615360

Preserveing and conducting, service and maintenance of electrical installations in Esfahan City Center Project

Employer : Iran Prestige Land Co.
Provoided Service : : Maintenance and reparing of equipment for 24 hours during the contract period
Duration : 36 months
Employer Address : North Railway Station Esfahan, Opposite of Southern Entrance of Sepahan Shahr, East of Vahid Dastjerdi Highway, Esfahan. Tel: 0311-6541900

192
Completed
Completed

Design, providing, Installation and commissioning of control system and instrumentation in Golpayegan Water Treatment

Employer : Zharf Kar-e Jam Co.
Provoided Service : Design of power and control systems, monitoring based on S7-300 Siemens hardware
Duration : 10 months
Employer Address : No.123, Mehrdad Building, Eastern Allameh Amini St. , Allameh Amini Intersection, 22 Bahman St. , Esfahan. Tel: 0311-2616516

Design, providing, Installation and commissioning of control system and instrumentation in Saveh Waste Water Treatment

Employer : Zharf Kar-e Jam Co.
Provoided Service : Design of power and control systems, monitoring based on S7-300 Siemens hardware
Duration : 10 months
Employer Address : No.123, Mehrdad Building, Eastern Allameh Amini St. , Allameh Amini Intersection, 22 Bahman St. , Esfahan. Tel: 0311-2616516

191
Completed